1. epoxy self-leveling thick film paint(2mm thick):
name of the paint |
paintingarea/kg |
used amount/㎡ |
thickness(about) |
epoxy sealing primer |
7㎡/kg |
0.14 kg/㎡ |
15um |
epoxy self-leveling intermediate coat paint |
0.67㎡/kg
(with sand) |
1.5
kg/㎡ |
0.5 kg/㎡ |
1085um |
quartz sand |
1 kg/㎡ |
epoxy floor self-leveling topcoat |
1.1㎡/kg |
0.9 kg/㎡ |
900um |
2. epoxy self-leveling thick film paint(3mm thick)
name of the paint |
paintingarea/kg |
used amount/㎡ |
thickness(about) |
epoxy sealing primer |
7㎡/kg |
0.14 kg/㎡ |
15um |
epoxy self-leveling intermediate coat paint |
0.3㎡/kg
(with sand) |
3
kg/㎡ |
1 kg/㎡ |
2085um |
quartz sand |
2 kg/㎡ |
epoxy floor self-leveling topcoat |
1㎡/kg |
1 kg/㎡ |
980um |
construction reference:
1. surface treatment: the water content of the cement is below 8%. the strength is qualified. remove the dirt and loose part. wear the surface with buffing machine. the surface parameter is within 1mm. remove the extra part with angle grinder or fill it with mortar. fill all the cracks and concave hole. the surface must be firm, dry and no dust.
2. roller coat the sealing primer: after the preparation work roller coat the sealing primer. brush the paint uniformly without any leaks. after 12 hours of drying do the next work.
3. paint intermediate coat paint: wear it after at least 12 hours when the primer is dry. paint the intermediate coat paint. mix the two compents according to the proportion and stir it. after 5 minutes brush it. ( use it up within 6hours or it will become blue) mix the paint and quartz sand according to the proportion of 3︰7 and stir it . brush two layers of mortar with scraper. the thickness depends on the regulation. brush next layer of mortar after 24 hours. maintain it for 24 hours. the next work can be done.
4. self-leveling topcoat(about 1mm thick): check the mortar whether it is dry. if it is qualified paint the topcoat with a trowel one time. mix the two components uniformly. deaerate and brush after 5 minutes of aging. use the paint up within 2 hours. deaerate the surface with needle roller. check the film with cleats on it. after it is qualified seal the site and avoid dust. maintain the site for 72 hours. then it can be used.